Practice is led by Ravish Bhatt | Advocate, Bar Council of Gujarat (G/504/2008) | Dual-qualified lawyer (India and England and Wales) | Solicitor of England and Wales (non-practising), SRA Registration No. 492 477 | ADIT, Chartered Institute of Taxation, London Published: 22 November 2026 | Last reviewed: 22 November 2026 |
| Scope. Written against sections 53, 73 and 74 of the Indian Contract Act, 1872, the FIDIC Conditions of Contract for Construction, 1999, the Society of Construction Law Delay and Disruption Protocol, 2nd edition (2017), and Supreme Court of India decisions up to Consolidated Construction Consortium Ltd v Software Technology Parks of India (28 April 2025). Extension of time evidence, the prevention principle and section 55 notice are covered in the delay evidence page; proof of loss for liquidated damages in the liquidated damages page. |
| Short answer. Mitigation and acceleration are different obligations, and the difference decides who pays. A contractor must take reasonable steps to limit the effect of a delay; it need not buy back the employer’s delay with extra shifts and plant at its own cost. Acceleration cost becomes recoverable when the employer orders it, agrees to pay for it, or forces it by withholding time that is due. No Supreme Court decision yet addresses constructive acceleration, so the record decides. |
Does a contractor have to accelerate at its own cost to mitigate a delay the employer caused?
| No. Section 73 of the Indian Contract Act, 1872 and Murlidhar Chiranjilal (1961) require reasonable steps to mitigate loss, and bar recovery of loss caused by failing to take them. Reasonable steps are resequencing, redeploying idle resources and working unaffected fronts. Extra shifts, extra plant and premium procurement are acceleration, which the general duty to mitigate does not require. |
The Explanation to section 73 provides that, in estimating loss from a breach, “the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account”. In Murlidhar Chiranjilal v Harishchandra Dwarkadas, AIR 1962 SC 366, the Supreme Court read section 73 and its Explanation as imposing “the duty of taking all reasonable steps to mitigate the loss consequent on the breach”, which “debars him from claiming any part of the damage which is due to his neglect to take such steps”.
The duty is to act reasonably, not to spend to cure the other side’s breach. The Society of Construction Law Delay and Disruption Protocol, an English practice guide that is persuasive only, puts it directly: “the duty to mitigate does not extend to requiring the Contractor to add extra resources” (Core Principle 15), and acceleration “typically refers to the situation where additional costs are incurred” (Guidance Part A, paragraph 12).
| Reasonable mitigation (expected) | Acceleration (not owed at own cost) |
|---|---|
| Resequencing activities around the unavailable area | A second or third shift |
| Redeploying idle labour and plant to unaffected fronts | Additional labour, subcontractors or plant |
| Continuing procurement and off-site fabrication | Premium freight or expedited procurement |
| Using float in the programme | Overtime premiums to recover critical-path time |
The contract can shift this. Under Sub-Clause 8.6 of the FIDIC 1999 Conditions of Contract for Construction, revised methods to expedite progress are “at the risk and cost of the Contractor”, but only where progress is slow “other than as a result of a cause listed in Sub-Clause 8.4”, and Sub-Clause 8.4(e) lists “any delay, impediment or prevention caused by or attributable to the Employer”. Employer delay therefore sits outside the contractor’s own-cost obligation. Bespoke EPC contracts often word this differently, and the clause, not the general law, then decides.
Directed, constructive or voluntary acceleration: which can the contractor recover?
| Directed acceleration, ordered by the employer or engineer, is paid under the contract, often as a variation: FIDIC 1999 Sub-Clause 13.1(f) treats changes to the sequence or timing of the works as one. Constructive acceleration is recoverable, if at all, as damages, and must be proved. Voluntary acceleration, to recover the contractor’s own delay, stays at the contractor’s cost. |
| Point | Directed acceleration | Constructive acceleration | Voluntary acceleration |
|---|---|---|---|
| How it arises | A written instruction or agreement to finish earlier than the contractor is entitled to | Time is due but refused or left undecided, and the employer insists on the original date | The contractor speeds up to recover its own delay or for its own commercial reasons |
| Basis of payment | The contract: a variation under Sub-Clause 13.1(f) in FIDIC 1999, or the agreed price | Damages under section 73 for the employer’s breach | None |
| What must be proved | The instruction and the cost | Entitlement to time, refusal or inaction, compulsion, and the extra cost | Not applicable |
| Main risk | Disputes over the price if it was not agreed first | The employer says the contractor accelerated by choice | The employer says the contractor was only catching up |
For the employer-caused case, the closest Supreme Court authority is K.N. Sathyapalan v State of Kerala, (2007) 13 SCC 43. Where one party’s failure directly affects the other’s work, “the Arbitrator is vested with the authority to compensate the second party for the extra costs incurred by him”, a principle the Court traced to P.M. Paul v Union of India, AIR 1989 SC 1034. The case concerned escalation, not acceleration. In the author’s view, acceleration cost forced by employer delay is the same kind of extra cost.
Section 53 of the Indian Contract Act, 1872 gives a contractor prevented from performing a right to compensation; how prevention works in a delay claim is covered in section 3 of the delay evidence page. How an instructed change is documented and valued is covered in the variation claims page.
Extension of time undecided and liquidated damages threatened: when does accelerating become a claim for constructive acceleration?
| In the author’s view, when five things are shown: a delay entitling the contractor to time; a timely extension request; refusal, or failure to decide; the employer holding it to the original date, usually by threatening liquidated damages; and acceleration actually undertaken at extra cost. No Supreme Court decision sets this test; it rests on section 73. |
The persuasive guidance points the same way. Core Principle 16 of the Delay and Disruption Protocol says that a contractor considering acceleration “as a result of not receiving an EOT that it considers is due, and then pursuing a constructive acceleration claim”, “should first take steps to have the dispute or difference about entitlement to an EOT resolved”.
In the author’s view, the record that turns acceleration into a claim is built in this order:
- Notice of each delay event and the extension claimed, within the contract’s time limits.
- A written request for a decision on the extension, citing the clause that requires one.
- A letter stating that insistence on the original date will require acceleration, with a priced proposal, and asking whether the employer instructs it.
- If there is no answer, a notice reserving the right to recover acceleration cost before the extra resources are mobilised.
- Separate cost codes for every acceleration measure from the day it starts.
- Referral of the extension dispute to the contract’s dispute procedure, so that entitlement is decided and not left open.
The employer’s answer will be that the contractor accelerated by choice, or to recover its own delay. The letters above are what defeat it. An extension granted later does not by itself remove the liquidated damages exposure: in Consolidated Construction Consortium Ltd v Software Technology Parks of India, 2025 INSC 574, extensions granted while “reserving its right to levy liquidated damages” left an award of liquidated damages standing (paragraphs 16, 17 and 28). How extensions interact with liquidated damages is covered in section 7 of the delay evidence page.
Should the contractor accelerate at all? Weighing acceleration cost against liquidated damages exposure
| Compare three figures: the cost of acceleration, the liquidated damages realistically at risk once a valid extension is allowed, and what the contractor loses if it does not accelerate, such as withheld payments or a called bank guarantee. Where acceleration costs more than that exposure and its recovery is uncertain, accelerating to beat a liquidated damages threat is rarely economic. |
Section 74 of the Indian Contract Act, 1872 caps liquidated damages at the amount named and allows only reasonable compensation within it. Whether an employer must show loss before deducting them is covered in the liquidated damages page. The decision here is commercial, and in the author’s view these factors decide it:
| Factor | Points towards accelerating | Points against accelerating |
|---|---|---|
| Extension entitlement | Weak or disputed on the critical path | Strong and well documented |
| Liquidated damages cap | High, and close to being reached | Low, or already near the cap |
| Acceleration cost | Modest and capable of being priced in advance | High, or likely to be lost to congestion |
| Employer response | Written instruction or agreed price | Silence, or refusal to engage |
| Other consequences of delay | Bank guarantee or milestone payments at risk | No security or payment tied to the date |
| Physical feasibility | Time can genuinely be recovered | The delayed area cannot be completed on time whatever is spent |
A middle course is often the sound one: carry out reasonable mitigation, offer acceleration as a separately priced option, and accelerate only on an instruction or an agreed price.
How is acceleration cost calculated and proved, and how is it kept apart from prolongation cost?
| Acceleration cost is the extra cost of finishing earlier than the contractor otherwise would have: overtime and shift premiums, additional labour and plant, premium procurement and productivity lost to congestion. It is proved from segregated records measured against the unaccelerated programme. Time recovered by acceleration cannot also be claimed as prolongation, or the same loss is paid twice. |
No statute or Supreme Court decision prescribes a formula. In the author’s view, the measure is the actual cost of the accelerated work less what the same work would have cost at the planned rate, head by head:
- Premium element of overtime and shift allowances, not the full wage.
- Additional labour, subcontractors and plant brought in for the acceleration, with their mobilisation and demobilisation.
- Premium freight and expediting charges above the planned procurement cost.
- Extra supervision for the added shifts.
- Productivity lost to congestion and stacking of trades, proved as disruption.
Illustration, on hypothetical figures: an employer delay of four months is reduced to two by acceleration. The contractor may claim the acceleration cost of recovering two months, and prolongation cost for the two months that remain. It cannot claim prolongation for four months as well as the acceleration cost.
Lost productivity is proved by the methods in Disruption and Loss of Productivity Claims, which also sets out the reconciliation that keeps idle, productivity and prolongation heads apart. Head office overheads and profit for the remaining delay, and what the Supreme Court requires before a formula is applied, are covered in Loss of Profit for Delay.
How R & D Law Chambers Works on These Matters
R & D Law Chambers LLP advises contractors and employers on extension of time, acceleration and delay claims under FIDIC and bespoke EPC contracts, and acts in arbitration on them seated in India and abroad.
Related services
- EPC contract advisory and dispute resolution across India
- International EPC advisory
- International arbitration seated in India and abroad
- Domestic and international arbitration from Ahmedabad
Related reading
- What Is the Most Important Evidence in a FIDIC Delay Claim in India?
- EPC Contracts in India Part 4: Commercial Risk
- FIDIC variation claims and their documentation
- Loss of Profit for Delay in Indian Construction Arbitration
- Disruption and Loss of Productivity Claims in Indian Construction Arbitration
| This page states the law as at 22 November 2026 for general information. It is not legal advice and does not create an advocate and client relationship. Whether acceleration cost is recoverable depends on the terms of the contract, the notices given and the records kept. |