Loss of Profit for Delay in Indian Construction Arbitration: The Hudson, Emden and Eichleay Formulae After Batliboi
| R & D Law Chambers LLP
Practice is led by Ravish Bhatt | Advocate, Bar Council of Gujarat (G/504/2008) | Dual-qualified lawyer (India and England and Wales) | Solicitor of England and Wales (non-practising), SRA Registration No. 492 477 | ADIT, Chartered Institute of Taxation, London Published: 21 November 2026 | Last reviewed: 21 November 2026 |
| Scope. Written against sections 55 and 73 of the Indian Contract Act, 1872, section 34 of the Arbitration and Conciliation Act, 1996, and Supreme Court of India decisions up to C & C Constructions Ltd v IRCON International Ltd (31 January 2025). It covers money claimed for delay to completion. Lost productivity during the works is covered in Disruption and Loss of Productivity Claims in Indian Construction Arbitration. Mitigation and acceleration are outside its scope. |
| Short answer. Hudson, Emden and Eichleay are three ways of pricing one assumption: that, but for the delay, the contractor would have earned the same overhead recovery and profit on other work. Since Batliboi v HPCL (2023), the Supreme Court requires that assumption to be proved, by tenders declined or turnover lost, before any formula is applied. The formula is the last step of the claim, not the first. |
Loss of profit or loss of profitability: which does a contractor claim for delay?
| They are different losses. Loss of profit is the margin on the contract work itself, recoverable when that work is wrongfully taken away. Loss of profitability is the earning capacity locked up by delay: overheads and resources held on one project that could have earned elsewhere. A delay claim is usually the second, and the three formulae measure only that. |
Loss of profit in the first sense rests on A.T. Brij Paul Singh v State of Gujarat, (1984) 4 SCC 59. The State had wrongfully repudiated a works contract. The Supreme Court held that a “reasonable expectation of profit is implicit in a works contract” (paragraph 10), and accepted 15 per cent of the value of the remaining work as the measure of the profit lost (paragraph 11).
Loss of profitability is the delay claim. The contractor does not lose the work; it performs it late, and its complaint is that its organisation was tied to the project for longer than it priced. In Bharat Coking Coal Ltd v L.K. Ahuja, (2004) 5 SCC 109 the Supreme Court held that such a claim requires the contractor to show it could have used the money on other business: “Unless such a plea is raised and established, claim for loss of profits could not have been granted.”
Batliboi Environmental Engineers Ltd v Hindustan Petroleum Corporation Ltd, 2023 INSC 850; (2024) 2 SCC 375 states the consequence. If loss of turnover caused by the delay is not established, “it is merely a delay in receipt of money”, and the contractor is generally confined to interest on the capital employed (paragraph 23).
| Loss of profit | Loss of profitability | |
|---|---|---|
| What is lost | Margin on work the contractor was prevented from doing | Earnings the organisation could have made elsewhere during the delay |
| Usual trigger | Wrongful termination or omission of work | Prolongation caused by the employer |
| Usual measure | Percentage of the value of the work not done (15 per cent in Brij Paul Singh) | Hudson, Emden or Eichleay, or the actual records |
| What must be proved | Breach, and the work lost | Breach, delay not caused by the contractor, and other work it would have secured (Batliboi, paragraph 23) |
| If the loss is not proved | The claim fails | Interest on the capital employed (Batliboi, paragraph 23) |
What are the Hudson, Emden and Eichleay formulae, and how do they differ?
| All three spread head office overhead across the delay, but take the percentage from different places. Hudson uses the overhead and profit percentage priced in the contract. Emden uses the contractor’s actual overhead and profit across its whole business. Eichleay allocates actual overhead by the project’s share of billings and prices each day of delay, without profit. |
The Supreme Court set out all three in McDermott International Inc v Burn Standard Co Ltd, (2006) 11 SCC 181. The arbitrator there had applied Emden, and the Court declined to interfere: sections 55 and 73 of the Contract Act “do not lay down the mode and manner” of computing damages, and the choice of formula is for the arbitrator.
| Formula | As set out in McDermott | Source of the percentage | Includes profit? | Weak point |
|---|---|---|---|---|
| Hudson | Head office overhead and profit percentage x contract sum x period of delay / contract period | The contract or tender pricing | Yes | Assumes the tender percentage was realistic; recovers overhead and profit twice if applied to the full contract sum (Batliboi, paragraph 25) |
| Emden | Same structure, with the percentage taken as total overhead and profit of the organisation as a whole / total turnover | The contractor’s accounts | Yes | A company-wide average may not reflect the delayed project |
| Eichleay | (Contract billings / total billings) x total overhead = allocable overhead; allocable overhead / days of contract performance = daily rate; daily rate x days of delay | The contractor’s actual overhead and billings | No | Requires the fixed overheads to be itemised and quantified (Batliboi, paragraph 24) |
Batliboi does not disturb McDermott. It adds that the formulae “deal with theoretical mathematical equations, but are based on factual assumptions” (paragraph 21), which must be shown to hold before the result is used, and it regards Eichleay as “far more nuanced and rigorous” because it works from itemised fixed overheads (paragraph 24). Why a formula can calculate a loss but cannot prove one is explained in section 8 of FIDIC variation claims and the documents that prove them.
How is loss of profit for delay calculated? A worked example
| On a ₹100 crore, 24-month contract delayed six months by the employer, the formulae give between ₹1.20 crore and ₹3.75 crore. Applying Hudson to the contract sum less its own overhead and profit, a modification Batliboi records, brings it to ₹3.19 crore. The spread itself explains why the Supreme Court treats Hudson as a last resort. |
The figures are illustrative. Assume:
- Contract sum ₹100 crore, with head office overhead and profit priced at 15 per cent of it (₹15 crore).
- Contract period 24 months (730 days); employer delay 6 months (182 days); the contract was therefore performed over 912 days.
- Over those 912 days the contractor billed ₹1,250 crore across all its projects, of which ₹100 crore on this contract, and incurred ₹75 crore of head office overhead.
- In its audited accounts, overhead and profit for a year are ₹60 crore on turnover of ₹500 crore: 12 per cent.
| Method | Calculation | Result |
|---|---|---|
| Hudson, as usually stated | 15% x ₹100 crore x 6/24 | ₹3.75 crore |
| Hudson, on the contract sum less overhead and profit (Batliboi, paragraph 25) | 15% x ₹85 crore x 6/24 | ₹3.19 crore |
| Emden | 12% x ₹100 crore x 6/24 | ₹3.00 crore |
| Eichleay (overhead only) | (100 / 1,250) x ₹75 crore = ₹6.00 crore; ₹6.00 crore / 912 days = ₹6.58 lakh a day; x 182 days | ₹1.20 crore |
Four adjustments decide what survives of these figures:
- Emden takes its percentage from the accounts, not the tender. Emden stated with the tender percentage is Hudson under another name.
- Variations “contain their own element of overheads and profits” (Batliboi, paragraph 25). Applying the percentage to a final account enlarged by variations recovers that element twice.
- Extended site overheads, such as site staff, plant hire, insurance and guarantee charges, are a separate head. Where they are claimed at actual cost, the formula must be confined to head office items, or the award overlaps (Batliboi, paragraph 26).
- The profit element in Hudson and Emden is recoverable only if the contractor proves the other work it lost. Without that proof, the remedy is interest on capital (Batliboi, paragraph 23).
Batliboi’s direction is that Hudson’s method should be used “as a last resort, where no other way to compute damages is feasible” (paragraph 26).
What must a contractor prove before a tribunal applies a formula after Unibros and Batliboi?
| That the formula’s assumptions are true on the facts. Batliboi names three: the tender was not underpriced, the profit priced was realistic, and comparable work at that profitability was available. The contractor must then prove it would have secured other work, by invitations to tender it declined for want of capacity, or accounts showing turnover fell because of the delay. |
The four conditions the Supreme Court set in M/s Unibros v All India Radio, 2023 INSC 931; (2024) 1 SCC 221 are set out in section 8 of What Is the Most Important Evidence in a FIDIC Delay Claim in India? and are not repeated here. Unibros held that Hudson’s formula “does not, however, apply in a vacuum” (paragraph 18). Batliboi supplies the content of the proof, in paragraphs 22 and 23. The documents that meet it are:
- Invitations to tender received during the delay, and the replies declining them for want of capacity.
- Audited accounts for the years before, during and after the delay, showing turnover and head office overhead.
- The tender build-up showing the overhead and profit percentage priced, to test the Hudson assumptions.
- For Eichleay, a schedule itemising the fixed head office overheads for the period of performance (Batliboi, paragraph 24).
An award that applies a formula without findings on these points is exposed under section 34. In Unibros the Supreme Court dismissed the contractor’s appeal against the setting aside of an award of loss of profit computed on Hudson’s formula, because the evidence of loss was missing. In Batliboi the Court held that “A conclusion without any discussion and reasons, is non-compliant” (paragraph 7), and that heads of claim which overlap cannot stand together (paragraph 27).
Does a no-damage-for-delay clause, or an extension of time accepted without protest, bar the claim?
| Usually, yes. The Supreme Court enforces clauses that give an extension of time instead of damages for employer delay, and an arbitrator who awards damages despite one exceeds jurisdiction. The routes around such a clause are narrow: an agreement or assurance that compensation will be paid, notice of the claim when late performance is accepted, or repudiation. |
In Ramnath International Construction (P) Ltd v Union of India, (2007) 2 SCC 453 the clause “amounts to a specific consent by the contractor to accept extension of time alone” (paragraph 13). In ONGC Ltd v Wig Brothers Builders and Engineers (P) Ltd, (2010) 13 SCC 377 the arbitrator “exceeded his jurisdiction in ignoring the said express bar” (paragraph 6). In M/s C & C Constructions Ltd v IRCON International Ltd, 2025 INSC 138 the contractor had sought extensions under clause 49.5 and undertaken not to claim beyond escalation, and was held estopped from challenging the clause (paragraph 19). Whether such a clause is void under sections 23 and 28 of the Contract Act was not decided: the point was raised for the first time in the Supreme Court and not entertained (paragraph 24).
The exceptions come from General Manager, Northern Railway v Sarvesh Chopra, (2002) 4 SCC 45. A claim for delay remains open where the contractor repudiates the contract under section 55; where the employer grants the extension by a supplemental agreement, or makes clear that escalation or compensation will be paid; or where the contractor makes clear that compensation must be paid and the employer accepts performance despite the delay. Under the last paragraph of section 55, a party that accepts performance at a time other than that agreed cannot claim compensation for the delay unless it gives notice of its intention to do so at the time of acceptance: see section 6 of the delay claim evidence page.
Asian Techs Ltd v Union of India, (2009) 10 SCC 354 allowed a claim despite a clause in the Ramnath form, because the delay was “solely due to the default of the respondents” and the contractor had continued on written assurances that rates would be settled. In the author’s view a contractor should not plan on Asian Techs. Ramnath and Wig Brothers treat the same kind of clause as a bar on the arbitrator, and the facts that carried Asian Techs, assurances of payment, fit the second Sarvesh Chopra situation in any event.
The practical answer lies in the extension application. Each request should reserve the claim for compensation in terms, and each acceptance of late performance should carry the section 55 notice. A request made under the clause without reservation is the conduct that estopped the contractor in C & C Constructions.
How R & D Law Chambers Works on These Matters
R & D Law Chambers LLP advises contractors and employers on claims for delay and loss of profit under FIDIC and Indian public works contracts, from the extension of time application to the statement of claim, and acts as counsel in the arbitration and in proceedings under sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
Related services
- EPC contract advisory and dispute resolution
- International EPC contract advisory
- International arbitration seated in India and abroad
- Domestic and international arbitration from Ahmedabad
Related reading
- What Is the Most Important Evidence in a FIDIC Delay Claim in India?
- FIDIC variation claims and the documents that prove them
- Liquidated damages and bank guarantees in EPC contracts
- Disruption and Loss of Productivity Claims in Indian Construction Arbitration
| This page states the law as at 21 November 2026 for general information. It is not legal advice and does not create an advocate and client relationship. The outcome of any claim depends on the terms of the contract and the records kept under it. |